“DUMSOR” Time Table Released by ECG.

NEWS

“DUMSOR” Time Table Released by ECG.

A timetable has released by the Electricity Company of Ghana (ECG) to manage the disruptions in power supply in parts of the Greater Accra Region.

This is as a result of the are ongoing system improvement works on the Pokuase Bulk Supply Point according to ECG.

In a press release, The exercise is expected to see the complete shutdown of the 330Kv line of the Mallam Bulk Supply Point (BSP).

Areas to be affected include Dansoman, Bubiashie, Mallam, Odorkor, Mamprobi, Pokuase ACP Estates, Sakaman, Laterbiokorshie, Sowutuom, Abeka La Paz, and others.

The timetable is expected to start on Monday, May 10 to May 17, 2021.

THE SCHEDULE BELOW.